48-core outdoor optical cable wiring is required for direct buried laying. I believe that many outdoor optical cable wiring workers have some understanding, but it is full of question marks for the novice who is just getting started. Today, I will summarize this problem for you. It can help you in your future work, let's take a look at the specific optical cable wiring requirements!
1. Before the communication optical cable is wired, reasonable learning and training should be carried out for the project construction and related staff on matters that should be paid attention to in the project construction, such as construction wiring skills essentials and safety protection, etc., and the construction safety personnel should be ensured to obey the command. .
2. Review the detailed direction of the wireless routing of the communication optical cable, the layout method, the indoor environmental conditions and the detailed site of the connection head whether it can fully comply with the construction drawing design.
3. Review the distance on the ground and the distance of the relay segment.
48-core outdoor optical cable manufacturers share optical cable wiring requirements
4. To review the specific address and correct handling measures of the area where protective measures should be taken when the communication optical cable passes through the regenerated obstacles.
5. Review the site, area and quantity of communication optical cable protection such as trench sills, sills, slope protection, and blockages.
6. The small distance between communication optical cable and other facilities, trees, buildings and underground pipelines should fully meet the technical standards for project acceptance.
7. The wireless routing direction, placement position and connection point of the communication optical cable should be safe and reliable, which is convenient for engineering construction and maintenance.
8. Before excavating the cable trench, the construction enterprise should design the gray line along the straight line of the gray line along the line according to the approved construction drawing.
9. The direct buried optical cable should be excavated according to the standard regulations.
10. Do not dig trenches, you can use overhead or drill holes for pre-buried pipelines.
11. Considering the heavy weight of the direct-buried optical cable for climbing and the complicated wiring terrain, the construction of this project is relatively difficult and requires a lot of labor costs, so there should be enough staff.
12. The bottom of the ditch should be gentle and firm, and some sand, cement or supports can be pre-filled when necessary.
13. When wiring 48-core outdoor optical cables, engineers and technicians should be equipped with necessary communication equipment, such as walkie-talkie speakers.
14. The bending radius of the communication optical cable should be less than 15 times the outer diameter of the communication optical cable, and it should not be less than 20 times during the construction process.
15. Labor cost or mechanical traction can be used during deployment, but attention should be paid to guidance and lubrication.
16. During mechanical traction, the progress adjustment range should be 3~15m/min, the adjustment method should be stepless speed regulation, and it should have automatic shutdown performance. During traction, methods such as centralized traction, assistance during traction, and decentralized traction should be selected according to factors such as traction length, terrain conditions, and traction tension.
17. After the wiring of the outdoor optical cable communication optical cable is completed, the end of the communication optical cable should be properly treated to prevent moisture, and it is strictly forbidden to soak in water.