Time:2023-02-06 Views:
1. Secret path wiring
The dark road and rich lines have been embedded in the floor pipes when pouring concrete. There are steel wires or iron wires in the pipeline. The installation staff only need to ask the pipeline drawing to understand the wiring pipe system of the floor. You can make a construction plan.
For old buildings or new buildings without embedded pipelines, they must ask the owner to ask the owner's drawings and go to the building site to be wiring. , Draw the wiring drawings in detail to determine the wiring construction plan.
For new buildings without embedded pipelines, the construction can be carried out in synchronization with the decoration of the building, which is convenient for the wiring without affecting the beauty of the building.
The pipeline is generally buried from the wiring room to the information socket installation hole. As long as the installation personnel fix the 4 pairs of cables on the line of the information socket, the gentry can be reached to the wiring room from the other end of the pipeline.
2. Circuit in the ceiling top
The most commonly used method of horizontal wiring is to wiring in the ceiling ceiling. The specific construction steps are as follows:
1) Determine the cloth line.
2) Follow the designed route, open the ceiling, push each inlaid with both hands, and multiple 4 pairs of lines are very heavy. In order to reduce the pressure on the ceiling, you can use J -shaped hooks, hangers and other supports. Come to support the cable.
3) Assuming that 24 pairs of cables should be distributed, 2 cables are installed on each information socket.
The cable box can be placed together and the cable takes over the mouth. There are 24 cable boxes in each group, with 4 groups in total.
4) Add bidding, write labels on the box, and mark the end of the cable.
5) Start at the farthest end of the management room, pull to the management room.
3. Wall line grooves rich line
The wiring slot on the wall generally follows the following steps:
1) Determine the cloth line.
2) Put the line along the routing direction (pay attention to the aesthetics of straight line)
3) Fixed screws are installed every 1m.
4) Wiring (70%wire slot capacity at the time of wiring)
5) Cover plastic groove cover. The cover should be dislocated.